2. Project Stardust38


 Stardust Rehab Deal

The Stardust Apartments is a 38-unit apartment property located at 1301 Stardust Street in Reno, NV. The building was constructed in 1963 and is composed of a wood frame with a concrete foundation, wood siding exterior and a pitched, composition shingle roof. The gross building area is 31,110 sqft. and includes 11 one-bed/one-bath units and 27 two-bed/one-bath units approximately 600 and 850 sqft. in size, respectively.

In December 2017, shortly after purchase of the property by MJD, the building caught fire and sustained significant damage to several units. With a budget of nearly $2.5 million, MJD is planning to completely renovated the entire property which will include interior improvements to each unit, as well as new roof, paint, paving and much more. The total construction timeline is expected to take approximately 18 months with half of the units becoming leasable within the first 6-9 months.

Rehab Details

Address:  1301 Stardust St
City Reno
County  Washoe
Year Build  1963
Area  31,110
Units  38
Acres:  0.85 Acres

 

***June 25, 2023****

1) Same update as last time. Continue to lease up the units.
2) Target to fully lease is still 3rd quarter.
3) Little slower leasing than anticipated.

***April 9, 2023 ****

1) Leasing process continues.
2) Target to fully lease it by 3rd quarter and then plan to put in on market.
3) Re-financed to lower rate by utilizing some internal capital

***Dec 19, 2022 ****

1) All the renovations completed
2) Leasing in progress, with a couple of tenants moved in
3) Marketing and re-rebranding in progress.

***Aug 31, 2022 ****

1. Leasing will begin within 30 days.
2. Full lease is expected to be completed by the end of Nov 2022
3. Self-walkthrough completed on Monday.

***July 13, 2022 ****
1) Repair work ETA is established to be end of July
2) Goal is to have the property fully lease by end of the year
***March 31, 2022 ****
1. Nearing completion of the East Building.
2. Estimated delivery date of June 10th.
3. Working on rebranding the complex to The Keystone.
4. Working on signage and creating the marketing for pre-leasing this asset.
***Jan 31, 2022 ****
1) We have our plumbing issues figured out
2) New completion date is June 2022
**** Oct 21, 2021 ****
1) Plumbing repairs in progress in West building
2) Full unit build-outs in progress in the East building.
3) Anticipated Mar 2022 completion
**** July 17, 2021 ****
1) Updates since purchase – Asbestos testing and abatement,
2) Cont.. Water and waste plumbing repairs, Shear nailing, carport repairs
3) Cont.. Framing, fencing, handrails, electrical, plumbing, windows
4) Cont.. landscaping, roofing
5) Next pending work.. interior and exterior finishing, remaining unit renovations
**** May 16, 2021 ****
1. Sewer lines replaced for all ground floor units
2. Leasing to be expected to start from August
3. Stucco, Insulation, Railing, HVAC work in progress
**** Jan 31,2021 ****
1) Renovation work in progress
2) Drywall delivered to be installed.

 **** Nov 28,2020 ****
1) Received Updated Construction Schedule.
2) Completed units will be turned over around April 2021
3) Leasing activities may start in early spring
**** Sept 26,2020 ****
1) About 25% completed in construction
2) Roofs, windows, framing, asbestos removal, stucco prep, and interior finishes ordering has all been completed
**** July 19,2020 ****
1) Permit received.
2) The site has been grubbed and construction started
3) Cabinets, Doors, and Windows ordered
4) Removed the Elevator shaft and Adjoining staircase
**** June 05,2020 ****
1) In the midst of COVID, continue to with contractors and city
2) Permitting process is quite involved
3) Working with Fire Marshal to resolve the fire sprinklers requirement
4) Seems pretty close to getting permits
 
**** April 07,2020 ****
1) Getting contractor bids
2) Permits to be pulled in about 5-6 weeks
 
**** Feb 08,2020 ****
1) Getting Bids from General Contractors after receiving city comments
2) Once bids are complied from several Contractors, we will resubmit
**** Dec 28,2019 ****
1) Still back and forth continues with the permits.
2) Fourth (hopefully last) revision ready for submission.
**** Oct 30 ,2019 **** 
1) Plans have been resubmitted. Expect to hear back any time now.
2) We anticipate some questions/additional information related to the insurance.
**** Sept 11,2019 **** 
1) Plans were submitted to the city and rejected
2) Engaging Insurance company to get approval for increase scope for permit
**** July 29,2019 **** 
 
1) Draft Plan is created and being reviewed.
2) After a few changes, it will be submitted to the city for review.
 
**** June 22,2019 ****
1) Started a new renovation project
2) Looking to raise some funds.
3) Please reach out to me if you would like more information.

ykrnew

Yajnesh Rai, Owner, Realtor

 BRE 01924991