Project Helen


Helen Rehab Deal

This is a joint venture project with GBC Properties, INC. GBC acquired an undeveloped land over a year ago and has completed partial development work. Our company has entered into a joint venture agreement to fund and work on this project to work along with GBC to complete it.
Needs to go through the remaining land development process, plans & permits, building a new house (# bedrooms, 3 bath, about 1800+ sq ft, and a detached garage). The project may take about a year to complete. Joint venture acquisition is $170k, build cost is about 450k and After Repair Value will be about 900k (a brand new house).


Rehab Details

Property City: Los Gatos
Property State: CA
Purchase Price:  $170k
Rehab + Other:  $450k
Money Cost:  $50k
Sale Price:
Gross Profit:


 

***Aug 31, 2022 ****

1) This project is currently on stand still. Waiting for some regulation changes from the city to move forward.

 

***July 13, 2022 ****

1). This project is currently on stand still. Waiting for some regulation changes from the city to move forward.

***March 31, 2022 ****

1). Architechs/Engg waiting for a new law to be passed to make it easier for approval

***Jan 31, 2022 ****

1) Continue pursuing the permit process with Architects, Civil Engg etc.

**** Oct 21, 2021 ****

1) Permit work still in progress
2) Working on Lot Survey, Road widening issues with the county

**** July 17, 2021 ****

1) Engineers working on county comments responses

**** May 16, 2021 ****

1. Working on replying to the County comments
2. Retained the existing Civil Engg for this additional work

**** Jan 31,2021 ****

1) Waste Management paperwork remaining before ready to re-submit

**** Nov 28,2020 ****

1) Working on revised plans according to new 2020 requirements

**** Sept 26,2020 ****

1) Planning work in progress.
2) Working on the revision of plans to meet new codes

**** July  19,2020 ****

1) Engineers and Architects are updating the file for new and updated codes for resubmitting.

**** June 05,2020 ****

1) Received everything from Engineers
2) Inquired with the City about Re-submitting
3) Working on School Fee & Waste Mgt Paperwork

**** April 07,2020 ****

1) Engaged with a new Structural Engg to completed the plans
Work in progress

**** Feb 08,2020 ****

1) Continue to work with Civil Engg, Structural Engg & Architect

***Dec 28, 2019 ***

1) Coordinating between Civil and Structural Engg

***Oct 30, 2019 ***

1) Working with Structural and Civil Engg for clearance letters

***Sept 11, 2019 ***

1) Chasing Engineers to get Letter of Explanation
2) Upon receipt of the letter, plans will be resubmitted to the city

***July 29, 2019 ***

1) Working with Engineers to complete the submission package.

***June 22, 2019 ***

1) Last of documents for final submission.

***May 18, 2019 ***

1) Working with Civil and Structural Engg to get letter for county

 

***March 30, 2019 ****

1) Working with Civil and Structural Engg for plans and calculations to resubmit to the county.

***Feb 23, 2019 ****

1) Drainage & Grading Engg hired
2) Plans being updated
3) Will then be re-submitted to the county

***Dec 23, 2018 ****

  1. Progress on this is quite slow from the Engg/Architechts
  2. Working on getting extensions

***Nov 24, 2018 ****

  1. Background work/Enginner-Architect work in progress

***Oct 27, 2018 ****

1) Few additional requirements from the county came in
2) Working with Architect and Engg(s) to get the drawings and certificates

***Sep 22, 2018 ****

1) Quite a few back and forth between County, Architech and Engg
2) Working with Architect and Engg to get the data that County needs

 

***Aug 25, 2018 ****

1) Waiting for response from Builging & Planning departments.

***July 28, 2018 ****

1) Planning Permits Comments has been recevived. 3 Departments pending.
2) Waiting on Building Comments

***June 23, 2018 ****

1) Final Packet Submitted for permits

***May 26, 2018 ****

1) Final Permit Package is being worked on. Planning to submit to City in couple of weeks.

***April 28, 2018 ****

1) Structural Engg Drawing Comlete
2) Putting packet together for submitting for permits

***March 24, 2018 ****

1) Continue to work with Structural Engg. and Architect.

***February 24, 2018 ****

1) Building Plans Are in Progress
2) Engages Structural Engg

*** Dec  30, 2017 ***

1) Land Approval Received
2) Working On Building Plans

*** Nov 23, 2017 ***

1) Public hearing in progress

*** Sept 23, 2017 ***

1) Land Development Complete
2) Working on Building Plans to be submitted

*** Aug 12, 2017 ***

1) Land Development Complete
2) Working on Building Plans to be submitted

*** July 01, 2017 ***

1) Submitted plans for Land approval
2) Waiting for County Review Comments

*** June 03, 2017 ***

1) Civil Engg Working on Road Widening Plan.
2) Next Step will be to Submit Site Plan to County For Approval.

*** April 22, 2017 ***

1. Civil Eng Report Being Prepared for Road Improvement
2. Plans will be submitted to planning after that

*** March 22, 2017 ***

1) Working with the County on Land Approval

*** March 04, 2017 ***

1. Making progress with the county on Land Approval.

*** December 31, 2016 ***

1) Additional reports/plan being developed for the city

*** December 17, 2016 ***

1) Working with Architects and County towards Approval steps.

*** December 03, 2016 ***

1) Civil Engg Report for Road Improvement Ready
2) Working on Submission Package to County

*** November 05, 2016 ****

1) Waiting for Civil Engg for Road Improvement Calculations

*** October 22, 2016 ****

1) Working with Civil Engg for Road Improvements.

*** October 08, 2016 ****

1) Regular Back and forth communication on the Land approval with County.

*** September 24, 2016 ****

1) New Planning Comments received from County

*** September 10, 2016 ****

1) More preparation work in progress for plans.

*** August 27, 2016 ****

1) Multiple communications with the city regarding site approval.

*** August 13, 2016 ****

  1. Architect working on floor plans.

      Floor plan

 

*** July 30, 2016 ****

1) No change in status since last update.

*** July 16, 2016 ****

1) Wating for subcontractors to complete reports.

*** July 03, 2016 ****

1) Preparation for submitting further documentation going on

*** June 19, 2016 ****

1) City needs Road Improvement feasibiity stury
2) Working on hiring a civil engg to do the above

*** June 05, 2016 ****

1) Waiting on County’s response to the Pre-Application

*** May  22, 2016 ****

1) Waiting for response from County

*** May  08, 2016 ****

1) Had Initial Review With County Officials
2) Planned for Next Steps…Minimum time it takes for this type of permits in 6-8 months.

*** April 24, 2016 ****

1) Architect Submited Initial Review Plan To City
2) Working on a Giant Tree Removal from Site

*** April 10, 2016 ****

1) Hired Architect
2) Preliminary Plans Submitted for Review

Site Plan

siteplan726

*** March 27, 2016 ****

1) Hired Architect
2) Working on home layouts for submitting to county

*** March 13, 2016 ****

1) Architect will be finalized coming week
2) Meeting with arborist for removing trees

***February 28, 2016 ****

1) Septic Design In Progress.
2) Negotiation With Two Architects.

***February 14, 2016 ****

1) Geology and Geo Technical Reports Complete
2) In the process of hiring architect

*** January 31, 2016 ****

1) Draft Geo Technical Report is Ready.
2) Re-Engaging Septic Consultant for Final Review & Approval.

*** January 17, 2016 ****

Waiting for Topo and Geo Reports.

*** January 03, 2016 ****

Waiting for Topo and Geo Reports.

*** December 20, 2015 ****

1) Machine Drilling for Geo Survey Completed.
2) Working with other trades.

*** December 06, 2015 ****

1) Geo Survey Phase 1 complete. Phase 2 (machine drilling to be scheduled)
2) Hiring process of other contractors/architects continues.

 

*** November 22, 2015 ****

1) Not much change in the status
2) Gathering required parties to do Soil Report, Geo Survey etc.

*** November 08, 2015 ****

1) Topology Survey Completed – waiting for final report
2) In the process of getting quotes to hire different contractors

 

*** October 24, 2015 **** 

1) Acquired new project as a Joint Venture
2) Land that needs to go thru development process
3) Getting Quotes for Topography Map and Geological Survey.


 

ykrnew

Yajnesh Rai, Owner, Realtor

 BRE 01924991